12
May. 2022
Photo report from the investment
17
Feb. 2022
Photo report from the investment
31
Jan. 2022
Building occupancy permit
31
Dec. 2021
Construction progress

Construction works have been completed. The investment is in the process of obtaining an Use Permit.

In progress: Works on the maintenance of greenery are in progress.

29
Nov. 2021
Construction progress

In progress: The assembly of balustrades in the galleries is in progress. Facade works have been completed. Works on the electrical, sanitary and ventilation installations are in progress. Works related to the development of the investment area are in progress. The assembly of the elevator has been completed. The floors of the balconies and the gallery of the mezzanine level were finished. The fence is being assembled. The following connections have been completed and accepted: power, plumbing, MPEC. The construction of the garage resin surface has begun. A garage door has been installed.

27
Oct. 2021
Construction progress

In progress: Installation of balcony railings on all buildings has been completed. The balustrades are being installed in the galleries. Insulation of the building is in progress, together with the installation of elevation bricks on building C and D. The assembly of the door system on building A, B, C and D has been completed. Electrical, sanitary and ventilation installations are in progress. Works related to the development of the investment area have commenced. The installation of sanitary, electrical and ventilation systems in the garage has been completed. The assembly of the elevator has started. The floors of the balconies and gallery of the mezzanine level were finished. The fence is being assembled.

10
Sep. 2021
Construction progress

In progress: Insulation of the building with the assembly of elevation bricks on building C and D, assembly of door system on building A, B, C and D. Assembly of balcony railings in building C. Assembly of gallery railings is in progress. Works on electrical, sanitary and ventilation installations are in progress. Works related to the development of the investment area have started. The garage hall lighting is being installed.

06
Aug. 2021
Construction progress

Completed: Plastering works in building A, B, C and D. Roof covering and roof flashings on building A, B, C and D. Installation of windows for buildings A, B, C and D. Installation of garage door fittings. Freon installations in buildings A, B, C and D were made.

In progress: Thermal insulation of the building and installation of elevation bricks on building C and D, installation of window system on building C and D. Installation of thermal insulation in the garage. The assembly of balcony balustrades for building A and B has started. Floor layers for buildings C and D. Work is underway on the electrical, sanitary and ventilation systems.

13
Jul. 2021
Construction progress

In progress: Plastering works in building C and D, thermal insulation of the building and installation of façade brick on building A, B and D, installation of window system on building B and D. Installation of thermal insulation in the garage has begun. The assembly of balcony railings in buildings A and B has started. The flooring layers of buildings A and B have started to be installed. Electrical, sanitary and ventilation installations are in progress. Freon installation in building A and B was made.

16
Jun. 2021
Construction progress

In progress: Plastering works in building B and C, thermal insulation of the building and installation of façade bricks on building A, B and D, installation of window system on building A, B and D. Electrical, sanitary and ventilation installations are in progress. The installation of thermal insulation in the garage has started.

24
May. 2021
Construction progress

In progress: Plastering works in building A and B, flashing of the roof in building A and B, thermal insulation of the building and installation of façade brick on building A and B, installation of window system on building A and B. Works on electrical, sanitary and ventilation installations are in progress.


Completed: Thermal insulation and waterproofing of the flat roof of the building/segment D

22
Apr. 2021
Construction progress

In progress: Masonry works on the partition walls of the building D. Electrical and sanitary installations on the "-1" floor and above the ground of the A, B and C building.

Completed: Installation of aluminum joinery of building A, B, C and D. Execution of thermal insulation and waterproofing of the flat roof of the building / segment A, B and C.

29
Mar. 2021
Construction progress

In progress: Masonry works on partition walls of building A, B, C. Installation of aluminum joinery of the BC and D building. Electrical and sanitary installations on floors “-1” and above-ground of building A and B. Execution of thermal insulation and waterproofing of the flat roof of the building / parts of B, C, D.

11
Mar. 2021
Construction progress

In progress: masonry works of the partition walls in the A part of the building. Installation of aluminum joinery of A and B. Electrical and sanitary installations on the “-1” floor. Execution of thermal insulation and waterproofing of the flat roof of the building / parts of A, B, C.

22
Feb. 2021
Construction progress

In progress: electrical and sanitary installations on the “-1” floor. Execution of thermal insulation and waterproofing of the roof of the building / part A.

03
Feb. 2021
Construction progress

Completed: open shell of buildings.

In progress: electrical and sanitary installations on the “-1” floor.

20
Jan. 2021
Construction progress

Completed: open shell of the buildings, reinforced concrete ceiling, bricklaying of partition walls of the garage storey.

In progress: bricklaying of storey walls, internal electrical installation.

05
Jan. 2021
Construction progress

Completed: walls of storey and reinforced concrete ceilings above the storeys. Rainwater storage reservoir with a ramp to the underground garage.

In progress: reinforced concrete ceilings of the storeys.

 

07
Dec. 2020
Construction progress

Completed: reinforced concrete foundations, walls of storey and reinforced concrete ceilings above the storeys.

In progres: bricklaying work of walls and reinforced concrete works of the floor ceilings.

16
Nov. 2020
Construction progress

Completed: reinforced concrete underground garage.

In progress: reinforced concrete works: foundation, walls and ground floor ceilings.

16
Oct. 2020
Construction progress

Completed: combined sewage connection, protection of the excavation.

In progress:  sanitary sewage system installation, foundation slab.

SEE MORE